Opinion · United States Court of Claims

Bell Aircraft Corp. v. United States

100 F. Supp. 661

Type
Opinion
Court
United States Court of Claims
Jurisdiction
Federal
Date
1951-10-02
Topic
general

*685HOWELL, Judge. Plaintiff sues to recover $2,286,819.95 alleged to be reimbursable items of cost incurred in the performance of four cost-plus-a-fixed-fee contracts (hereinafter referred to as CPFF contracts) for the manufacture and delivery of military aircraft known as P-39’s or Airacobras, entered into with defendant through the United States Army Air Corps.1 Of the total sum claimed to be due under the contracts, $1,035,918.73 represent experimental and development expense, and $1,250,901.22 represent production tooling cost.2 It is plaintiff’s contention that the sum in suit represents allowable costs which should have been reimbursed pursuant to all four CPFF contracts which provide in pertinent part as follows: “Article 3 (b). For the purpose of determining the amount payable under this contract, allowable items of cost will be determined by the Contracting Officer in accordance with regulations for determination of the cost of performing a contract as promulgated by the Treasury Department in Section 26.9 of Chapter 1 of Title 26 of Code of Federal Regulations, as contained in T. D. 5000 and approved by the Secretary of War August 2, 1940. * * * “Article 6 — Payments. “(a) Reimbursement for Cost. The Government will currently reimburse the Contractor for such expenditures made in accordance with Article 3 hereof as may be approved or ratified by the Contracting Officer and upon certification to and verification by the Contracting Officer of the original signed payr…

Citator

UpLaw has not yet analyzed Bell Aircraft Corp. v. United States. The absence of a flag is not a finding that it is good law.

Authority status
pending
Cited by
12 opinions