Opinion · Supreme Court of the United States

Priebe & Sons, Inc. v. United States

332 U.S. 407

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1947-11-17
Topic
general

How later courts describe this case

  • observing that “[tjoday the law does not look with disfavor upon ‘liquidated damages’ provisions in contracts! ] [wjhen they are fair and reasonable attempts to fix just compensation for anticipated loss caused by breach”
  • observing that “[t]oday the law does not look with disfavor upon ‘liquidated damages’ provisions in contracts! ][w]hen they are fair and reasonable attempts to fix just compensation for anticipated loss caused by breach”
  • describing contractual penalties as oppressive and unjust based on common law of contracts, not constitutional principles
  • “It is customary, where Congress has not adopted a different standard, to apply to the construction of government contracts the principles of general contract law”
  • Liquidated damages provisions "serve a particularly useful function when damages are uncertain in nature or amount or are unmeasurable[.]”
  • “It is customary ... to apply to the construction of government contracts the principles of general contract law”
  • liquidated damages are enforceable “[w]hen they are fair and reasonable attempts to fix just compensation for anticipated loss caused by breach of contract”
  • "[We] apply to the construction of government contracts the principles of general contract law."

Citator

UpLaw has not yet analyzed Priebe & Sons, Inc. v. United States. The absence of a flag is not a finding that it is good law.

Cited by
258 opinions

Headnotes

  1. Contracts Law — Interpretation Where a government contract specifies a date that "shall be the first day of a 10-day period within which the [buyer] will accept delivery, the particular day within the period being at the [buyer's] option," the time for the seller's delivery is not the first day of that period but the time or times chosen by the buyer within the period; performance is not due until the buyer requests delivery and gives instructions. 332 U.S. at 410
  2. Contracts Law — Liquidated Damages Where Congress has not adopted a different standard, the construction and enforceability of provisions in government contracts, including provisions for liquidated damages, are governed by the principles of general contract law. 332 U.S. at 411
  3. Contracts Law — Liquidated Damages Liquidated damages provisions in contracts are not disfavored and will be enforced when they are fair and reasonable attempts to fix just compensation for anticipated loss caused by breach, and they serve a particularly useful function where damages are uncertain, unmeasurable, or difficult to prove; such provisions are judged as of the time the contract was made, and the fact that the damages actually suffered prove less than the amount contracted for is not fatal to enforcement. 332 U.S. at 411-12
  4. Contracts Law — Liquidated Damages A provision styled as one for liquidated damages is unenforceable as a penalty where it does not cover delays in delivery but applies only to a failure to have goods inspected and ready by a date before delivery is due — a default that could not interfere with or delay prompt performance — because such a provision cannot possibly be a reasonable forecast of just compensation for damage caused by breach and operates merely as an added spur to performance. 332 U.S. at 412-13
  5. Contracts Law — Penalties — Deterrent Effect Although all provisions for damages are deterrents of default, an exaction of punishment for a breach that could produce no possible damage is oppressive and unjust, and courts will not give their imprimatur to arrangements whose purpose is not to make a fair estimate of damages but to serve only as an added spur to performance. 332 U.S. at 413
  6. Federal Government Contracts — Implied Powers — Penalties The power to impose penalties as sanctions on a procurement program may not be implied from a broad grant of authority to purchase on appropriate terms and conditions under the Lend-Lease Act, absent express congressional authorization; otherwise any procurement officer, in war or in peace, could impose them, contrary to the premise underlying the decisions governing government contracts. 332 U.S. at 413-14