Opinion · Supreme Court of the United States

Mankin v. United States Ex Rel. Ludowici-Celadon Co.

215 U.S. 533

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1910-01-17
Topic
general

Mr. Justice Day delivered the opinion of the court. This is a writ of error to the Circuit Court of Appeals for the Fifth Circuit, wherein a judgment of the Circuit Court of the United States for the Southern District of Mississippi in favor of the defendants in error was affirmed. The facts are: The Mankin Construction Company on February 27, 1905, enteréd into a contract with the Secretary of the Treasury for the-con *536 struction of a certain post-office building in the city of Natchez, Mississippi, and gave bond under the act of February 24,1905, .(33 Stat. 811, c. 778), amending the act of August 13, 1894, (28 Stat. 278, c. 280). This bond was conditioned that the Mankin Construction Company should “ promptly make payment to all persons supplying them labor or materials in the prosecution of the work contemplated by said contract.” Upon this bond the Title, Guaranty & Trust Company of Scranton, Pa., was surety.

Citator

UpLaw has not yet analyzed Mankin v. United States Ex Rel. Ludowici-Celadon Co.. The absence of a flag is not a finding that it is good law.

Cited by
81 opinions

Headnotes

  1. Federal Government Contracts — Payment Bonds — Labor and Material Act Under the federal labor and material act of February 24, 1905, indemnity on a payment bond given for the construction of a public building extends to persons furnishing labor and materials to a subcontractor as well as to those furnishing them directly to the contractor in chief. 215 U.S. at 538–539
  2. Federal Government Contracts — Payment Bonds — Scope of Recovery The indemnity afforded by the federal payment bond reaches the full amount of labor and materials furnished, notwithstanding that the contractor may have already paid the subcontractor in full or in part before receiving notice of the materialmen's claims; the federal act contains no notice requirement or limitation upon the contractor's liability. 215 U.S. at 540–541
  3. Federal Government Contracts — Federal Statute — Preemption of State Law Provisions in state statutes and mechanics' lien acts limiting a contractor's liability to the amount remaining unpaid to the subcontractor at the time of notice do not govern suits on bonds given under the federal labor and material act, which contains no such limitation and requires payment to all persons supplying labor and materials in the prosecution of the work. 215 U.S. at 541
  4. Federal Government Contracts — Statutory Construction — Binding Precedent The phrase "persons supplying the contractor with labor and materials," carried unchanged from the act of August 13, 1894, into the amending act of February 24, 1905, retains the meaning settled for the original statute—that it includes persons furnishing labor and materials to a subcontractor—and the additional procedural provisions of the amended act for obtaining a copy of the contract and bond for purposes of suit do not change or limit that obligation. 215 U.S. at 538–540