Opinion · Supreme Court of the United States

Plumley v. United States

Plumley v. United States, 226 U.S. 545 (1913)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1913-01-06
Topic
general

Mr. Justice Lamar delivered the opinion of the court. In October, 1888, P. H. McLaughlin & Company contracted to build the Naval Observatory in Washington *546 for $307,811.

Citator

UpLaw has not yet analyzed Plumley v. United States. The absence of a flag is not a finding that it is good law.

Cited by
76 opinions

Headnotes

  1. Contracts Law — Government Contracts — Finality of Secretary's Decision Where a contract for Government work provides that any discrepancy between the specifications and the contract shall be referred to the Secretary of the department making the contract, and the contractor agrees to abide by the Secretary's decision in the premises, the Secretary's construction of the contract and decision on the matter are final and conclusive and bind the contractor. 226 U.S. 545 (opinion, point 1)
  2. Contracts Law — Government Contracts — Written Authorization of Changes Where a contract for Government work requires that every change increasing or diminishing the cost be agreed in writing by the contractor and the architect, with a statement of prices, and be approved by the Secretary, a contractor cannot recover for extra work that was not ordered by the officer and in the manner the contract prescribes, even though the work was in fact extra and of value; the hardship of the case does not excuse compliance with the prescribed method. 226 U.S. 545 (opinion, point 3)
  3. Contracts Law — Government Contracts — Notice of Delay Where a contract for Government work requires the contractor to notify the Secretary of the cause of any delay at the time it occurs, so as to enable the Department to remove the cause, the contractor's failure to give such notice bars recovery for damages caused by the delay. 226 U.S. 545 (opinion, point 4)