Opinion · Supreme Court of the United States

Day v. United States

Day v. United States, 245 U.S. 159 (1917)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1917-11-26
Topic
general

How later courts describe this case

  • river levy construction contractor held liable for increased cost of levy due to delay caused by river flooding
  • “[W]hen the scope of the undertaking is fixed, that is merely another way of saying that the contractor takes the risk of the obstacles to that extent.”

Citator

UpLaw has not yet analyzed Day v. United States. The absence of a flag is not a finding that it is good law.

Cited by
77 opinions

Headnotes

  1. Contracts Law — Risk of Nonperformance A party who makes a contract cannot be absolutely certain of performance when the time comes, and the essence of the contract is that he assumes the risks of intervening obstacles within the limits of his undertaking; the modern tendency to determine the scope of the undertaking by intent rather than by the literal meaning of the words does not alter this principle. 245 U.S. at 161
  2. Contracts Law — Scope of Undertaking — Allocation of Risk Once the scope of a contractor's undertaking is fixed, the contractor bears the risk of the obstacles to that extent, and a provision contemplating that performance may be prevented by floods or other forces of nature, which affords only a discretionary extension of time, does not qualify the absoluteness of the contractor's promise to complete the work. 245 U.S. at 161-162
  3. Contracts Law — Implied Contract — Recovery of Voluntary Expenditures Where a contractor, though not obligated by the contract to do so, erects temporary defences against water for its own interest and safety, the cost cannot be shifted to the other party in the absence of an actual contract to pay for it. 245 U.S. at 162