Opinion · United States Court of Claims

Chernick v. United States

Chernick v. United States, 178 Ct. Cl. 498 (Ct. Cl. 1967)

Type
Opinion
Court
United States Court of Claims
Jurisdiction
Federal
Date
1967-07-25
Topic
general

How later courts describe this case

  • determining whether contracting officer had constructive knowledge of arithmetical mistake in bid
  • contracting officer should have known of bid mistake
  • correcting bid mistake by reforming contract price

Citator

UpLaw has not yet analyzed Chernick v. United States. The absence of a flag is not a finding that it is good law.

Cited by
59 opinions

On July 25, 1967, the court ordered that judgment be entered for the plaintiffs in the sum of $11,952.15. On December 11, 1967, the court vacated the order of July 25, 1967, and entered judgment for plaintiffs in the sum of $13,004.50.