Opinion · Supreme Court of the United States

United States v. Howard P. Foley Co.

United States v. Howard P. Foley Co., 329 U.S. 64 (1946)

Type
Opinion
Court
Supreme Court of the United States
Jurisdiction
Federal
Date
1946-11-25
Topic
general

Mr. Justice Black delivered the opinion of the Court. The Court of Claims rendered a judgment for the respondent and against the Government for an asserted breach of a construction contract. 105 Ct. Cl. 161, 63 F. Supp. 209.

Citator

UpLaw has not yet analyzed United States v. Howard P. Foley Co.. The absence of a flag is not a finding that it is good law.

Cited by
81 opinions

Headnotes

  1. Federal Government Contracts — Delay Damages The Government is not liable in damages for delay in making the work site available to a contractor under a construction contract where the contract neither expressly nor impliedly obligates the Government to make the site promptly available, but instead anticipates government-caused delays and provides remedies other than damages. 329 U.S. at 66-67
  2. Federal Government Contracts — Implied Warranty A contractual obligation on the contractor to complete the work within a specified time cannot be inverted into an implied unqualified warranty by the Government to make the work site promptly available, particularly where the Government's representatives performed their work with great diligence and no fault is attributable to them. 329 U.S. at 66
  3. Federal Government Contracts — Anticipated Delays and Remedies Where a Government construction contract contains provisions reserving the Government's right to make changes causing interruption and delay, requiring the contractor to coordinate its work with other work on the site, and establishing a procedure for extending completion time and relieving the contractor of termination or liquidated damages when delay is caused by acts of the Government or other specified events, the contract imposes no obligation on the Government to pay damages for delay. 329 U.S. at 67
  4. Federal Government Contracts — Contractor's Foreseeability of Delay The absence of a prime contractor does not distinguish a delay case from prior decisions holding the Government not liable for delay; where the contract terms and extrinsic facts show that changes and delays were anticipated and remedies therefor provided, the contractor's lack of a prime contract from which to read that indication is a distinction without significant difference. 329 U.S. at 68